Updated Information on the Ardingly Astana Project

Ardingly Astana LLP provides an update on the implementation of the project “Construction of a private day and boarding school based on the British model of education.”

As of 30 September 2026, the project is progressing in accordance with the approved implementation schedule.

The following key stages of construction have been completed:

  • preparatory works;
  • substructure (zero cycle) works;
  • monolithic construction works;
  • walls and partitions;
  • roofing and steel structure works;
  • installation of window units;
  • external utility networks;
  • façade works;
  • equipment and material supply works.

The remaining works under the project are currently nearing completion, including the interior finishing works, landscaping and site improvement works.

The construction of the new campus represents a key milestone in the implementation of the Ardingly Astana project and will provide a modern educational environment aligned with international standards.

The project envisions a comprehensive educational ecosystem, including advanced academic facilities, STREAM laboratories, creative studios, and modern sports infrastructure, as reflected in the project renderings.